Managing the Hybrid Pivot with Agile Test Infrastructure and Auto Test Equipment
October 20, 2026 -
Tags: Automotive and Commercial Vehicles, Battery/Electrification, Energy
Balancing Hybrid Realities with the Infrastructure Required for Electric Vehicles
After years of aggressive moves towards greater research and production in Electric Vehicles (EV), many automakers are delaying their near-term EV programs. Regulatory changes and market forces have led them to slow down their EV ambitions. Test infrastructure that’s gone under or unused now needs to get back online, often in facilities that haven’t had meaningful upgrades in decades, leaving engineers keeping 30-year-old dynos running by sourcing parts wherever they can find them – including eBay.
With uncertainty about where the auto market will be in a few years, manufacturers have little appetite for major capital projects. Their challenge is how to invest wisely in the infrastructure required for electric vehicles and their test equipment so they can support today’s shift to hybrids, while staying flexible enough to pivot when the next new direction arrives.
New Equipment Hits the Power Ceiling
A consistent issue we see with auto test equipment upgrades in older facilities is lack of electrical infrastructure. New dynos, higher-power drive cabinets, and updated test stands demand more power than the systems they’re replacing or the facility has, and the older facilities weren’t built with the infrastructure required for electric vehicles and higher-demand test procedures.
Completely overhauling the facility’s electrical infrastructure might temporarily solve the problem, but getting funding for such a project, especially a temporary fix, isn’t realistic right now. Explosive demand from data centers has manufacturers suffering long lead times and rising costs as they compete with them for electrical components and labor. Instead, automakers will need to get creative in how they approach adding electrical capacity to keep the upgrades’ cost within an approvable budget range.
For one of our recent projects, we split the facility into two separate electrical zones. We kept the existing feed serving one zone, effectively increasing that floor space’s capacity to handle upgraded equipment. We are then designing a new electrical solution to support the second zone, increasing the facility’s overall capacity without a teardown or a full-facility upgrade – all while keeping part of the facility running throughout construction.
Risk Assessments Set Upgrade Priorities
The first step is conducting a thorough risk assessment to set upgrade priorities. We work with clients by walking through each system, its equipment and subsystems, asking two questions: How likely is this to fail, and what happens if it does? A dyno with no available replacement parts and no workaround is a higher risk failure than one with a temporary fix. The assessed risk profiles provide documentation for a defensible, phased approach to upgrades.
Executives approving funds are wary of major spending after years of heavy EV investments that resulted in major write-downs and limited returns. A phased, multi-year approach is more palatable: tackle the highest-risk systems first, and schedule lower-risk projects over a three-to-five-year timeline. With systemic risk assessments ongoing and upgrade costs estimated, manufacturers keep a clear line of sight into where their investment is most needed to support the essential infrastructure required for electric vehicles.
Containing Upgrades while Leaving Room for the Future
A common instinct when planning upgrades is to maximize capacity while you have the chance to make changes, assuming that “future-proofing” means buying as much capacity as you can now. Designing in flexibility is critical, but that doesn’t require overspending on auto test equipment and systems today.
On a recent dyno replacement project, the initial request was for twelve large, high-capacity systems throughout the facility. We took a closer look at the automaker’s planned use cases and test plans, and found they outlined more modest operational requirements that could be met with two large systems and ten medium ones.
Instead of going with the original plan, which would have had them paying for dyno power, drives and electrical infrastructure they might never use, we designed a system that meets their current demands while preserving flexibility. The two high-capacity systems use more powerful, higher-torque dynos, and the ten medium-capacity systems all run on a shared, common-bus architecture tied into an electrical design they can adapt in the future to meet new testing needs.
The challenge and opportunity for automakers right now is defining a deliberate, risk-informed approach that right-sizes today’s investment while including the paths for future adaptability.